St. George development tracker

Suntran Transit Facility

St. George is building a new Suntran transit facility at 433 East Brigham Road that will serve every Suntran route and include six maintenance bays, offices, a fueling station and parking for customers and the city's bus fleet. Bonneville Builders received the construction contract in September 2025, work began later that year, and the city says the project remains on schedule for completion in December 2026. For the Oct. 22 meeting staff asked the council to approve a $663,239.24 change order, Bonneville's potential change order 026, to add the automotive equipment the six bays need (the pieces attached to the building or installed during construction). It consists of $631,656.42 of equipment plus 5% overhead and profit of $31,582.82. Bonneville would subcontract the equipment to Automotive Equipment of Nevada at the city's request and cut its fee from 10% to 5%, in exchange for the city bearing the cost of any scope gaps, design issues or delays from that subcontractor. Staff say the purchase was budgeted in the construction budget and is paid from the Public Transit Fund through a state grant for the Zion route. The change order in the packet is marked pending and not executed, so it is a proposal until the council acts; the result and any payment are not in the posted record.

Where it stands
Under construction
Type
Public project
Status evidence date
Thu, Oct 22
Location
433 East Brigham Road

Updates

  1. October 22, 2026

    Council agenda item 2c: approval of the $663,239.24 equipment change order. The packet copy of the change order was unsigned by the city and not marked paid. Source

Follow the money and project delivery

Suntran Transit Facility

Under construction

  1. Council action

    Under construction according to the dated project source. Record → · Oct. 22, 2026

  2. Money in the record

    change-order: $663,239.24 — Automotive equipment for six maintenance bays, Suntran Transit Facility Record → · Oct. 22, 2026

  3. Signed agreement and payments

    Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.

  4. Work and operating costs

    Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →

Every hearing and vote

  1. October 22, 2026 · City Council

    Suntran Transit Facility change order

    Pending

    The council was asked to approve a change order to the construction contract for the new Suntran Transit Facility. It adds automotive equipment for the six maintenance bays that is attached to the building or must be installed during construction.